Current network status and maintenance
Planned maintenance: 1089 - Cape Town Data Centre move - 7 February 2025 (batch 1)
Updates
-
Feb 8, 2025 1:05 AM SAST
Our Data Centre Engineers have completed the relocation of servers affected during this session and servers are now back online. Affected email and websites will now be reachable again.
Completed -
Feb 7, 2025 11:15 PM SAST (1 hour and 50 minutes earlier)
The servers have arrived at the new data center and will be connected soon.
Completed -
Feb 7, 2025 9:55 PM SAST (1 hour and 19 minutes earlier)
The shutdown of servers has been initiated and relocation to the new data centre will begin shortly.
Completed -
Feb 5, 2025 10:01 AM SAST (2 days, 11 hours, and 53 minutes earlier)
Maintenance window: 8hr
Attending: xneelo Engineers
Summary: The following servers will be unavailable due to the relocation of our Cape Town Data Centre:
dedi142.cpt4.host-h.net
dedi143.cpt4.host-h.net
dedi163.cpt2.host-h.net
dedi6.cpt4.host-h.net
dedi72.cpt4.host-h.net
dedi78.cpt4.host-h.net
dedi80.cpt4.host-h.net
dedi367.cpt4.host-h.net
dedi114.cpt4.host-h.net
dedi192.cpt4.host-h.net
dedi128.cpt4.host-h.net
dedi156.cpt4.host-h.net
dedi132.cpt4.host-h.net
dedi84.cpt4.host-h.net
dedi22.cpt4.host-h.net
dedi23.cpt4.host-h.net
dedi40.cpt4.host-h.net
dedi41.cpt4.host-h.net
dedi43.cpt4.host-h.net
dedi47.cpt4.host-h.net
dedi76.cpt4.host-h.net
dedi81.cpt4.host-h.net
dedi214.cpt4.host-h.net
dedi4.cpt1.host-h.net
dedi2.cpt4.host-h.net
dedi191.cpt4.host-h.net
dedi159.cpt4.host-h.net
dedi193.cpt4.host-h.net
dedi202.cpt4.host-h.net
dedi261.cpt4.host-h.net
dedi30.cpt1.host-h.net
dedi7.cpt4.host-h.net
dedi334.cpt4.host-h.net
dedi71.cpt4.host-h.net- Symptoms: Websites and email hosted on the affected server will be inaccessible during the maintenance window. For FAQs refer to our Help Centre article: https://xneelo.co.za/help-centre/products-and-services/data-centre-move-faq/
Scheduled