Current network status and maintenance
Feb 25, 2025 10:00 PM SAST
Planned maintenance: 1155 - Cape Town Data Centre - Automatic Transfer Switch Maintenance
Updates
-
Mar 3, 2025 9:26 AM SAST
The scheduled maintenance has been completed.
Completed -
Feb 25, 2025 10:00 PM SAST (5 days, 11 hours, and 26 minutes earlier)
Maintenance window: 2 Hours
Attending: xneelo Engineers
Summary: An interlocking and communications cable needs to be installed between the Automatic Transfer Switch on the A and B feed.
The work requires one power feed to be isolated at a time.
Symptoms: Due to the redundant design of the power architecture, single power corded devices will be protected for the duration of the maintenance window. In the event of a feed failure, the UPS and generator will provide backup power
Scheduled