Current network status and maintenance

Current network status and maintenance

Back
Jan 2, 2025 7:03 PM SAST

Planned maintenance: 988 - Limited Backup and Restore functionality for CPT2 and CPT3 hosts

Updates

  • Jan 3, 2025 10:31 PM SAST

    The scheduled maintenance has been completed.

    Completed
  • Jan 2, 2025 7:03 PM SAST (1 day, 3 hours, and 27 minutes earlier)
    • Maintenance window: 8 hr 45 min

    • Attending: xneelo Engineers

    • Summary: Backups that are scheduled to start later than 06:15 AM will only take place once the relocation has been completed and the backup schedule resumed.
      This will effect CPT2 and CPT3 hosts in our Cape Town Datacenter.

    • Symptoms: Limited backup and restore functionality

    Scheduled