Planned Maintenance: Samrand Data Centre Generator Commissioning

Resolved Date: 20 Jun 2020 15:42 SAST
Notice ID: #5945
Start: 20 Jun 2020 07:00 SAST
Maintenance Window: 14 hours
Attending: Xneelo engineers
Additional Information: No UPS power will be affected during the service routine.

Symptoms:

We will be connecting and commissioning generator B2.