Incident History
History
February 11 6:00 PM SAST until February 18 8:00 PM SASTPlanned maintenance: 1110 - Cape Town Preventative Fibre Maintenance
Completed
February 13 11:12 PM SAST
Scheduled
February 11 10:43 AM SAST
- Maintenance window: 2 Hours
- Attending: xneelo Engineers
- Summary: Our third party Fibre provider has scheduled maintenance that may affect our current fibers on that path. We will therefore move the fibre paths to run over our primary fibre provider to avoid being affected by fibre works on the third party’s path.
- Symptoms: No downtime is expected.
Planned maintenance: 1108 - Cape Town Data Centre move: Infrastructure servers
Completed
February 11 12:58 PM SAST
In Progress
February 11 12:57 PM SAST
In Progress
February 11 11:12 AM SAST
Scheduled
February 10 4:34 PM SAST
- Linux installations
- Rescue System
- Server monitoring
- Operating System (OS) Installations
- Remote Management Interface (RMI) Resets
Emergency maintenance: 1107 - www71.cpt1.host-h.net hardware replacement
Completed
February 10 10:47 AM SAST
Scheduled
February 10 9:54 AM SAST
- Maintenance window: 30 min
- Attending: xneelo Engineers
- Summary: www71.cpt1.host-h.net hardware swap out
- Symptoms: Websites and email hosted on the affected server will be inaccessible during the maintenance window.
Planned maintenance: 1096 - Cape Town Data Centre move - 10 February 2025 (batch 3)
Completed
February 10 3:15 AM SAST
Completed
February 10 2:19 AM SAST
Completed
February 10 12:45 AM SAST
Scheduled
February 7 9:28 AM SAST
- Maintenance window: 5hr 30min
- Attending: xneelo Engineers
- Summary: The following servers will be unavailable due to the relocation of our Cape Town Data Centre:
- Symptoms: Websites and email hosted on the affected server will be inaccessible during the maintenance window. For FAQs refer to our Help Centre article: https://xneelo.co.za/help-centre/products-and-services/data-centre-move-faq/
Planned maintenance: 1102 - Email Support and Webmail access
Completed
February 10 3:40 AM SAST
Scheduled
February 7 5:19 PM SAST
- Maintenance window: 2 hr 30 min
- Attending: xneelo Engineers
- Summary: Several of our servers will be moving from our Great Westerford Data Centre to the Open Access Data Centres in Brakenfell (Cape Town) on the 10th of February 2025.
- Email Support: Our ability to assist you via email.
- Webmail Access: Access to mailboxes for domains with email services hosted in Cape Town.
- Symptoms: Email support from our team may be delayed and Webmail will not be accessible for Cape Town hosted mailboxes.
Planned maintenance: 1095 - Cape Town Data Centre move - 9 February 2025 (batch 2)
Completed
February 10 1:33 AM SAST
Completed
February 10 12:44 AM SAST
Completed
February 9 11:17 PM SAST
Scheduled
February 7 9:26 AM SAST
- Maintenance window: 6hr 45min
- Attending: xneelo Engineers
- Summary: The following servers will be unavailable due to the relocation of our Cape Town Data Centre:
- Symptoms: Websites and email hosted on the affected server will be inaccessible during the maintenance window. For FAQs refer to our Help Centre article: https://xneelo.co.za/help-centre/products-and-services/data-centre-move-faq/
Planned maintenance: 1099 - www59.cpt1.host-h.net hardware upgrade 2nd phase
Completed
February 7 11:30 AM SAST
Scheduled
February 7 11:25 AM SAST
- Maintenance window: 1hr
- Attending: xneelo Engineers
- Summary: 2nd phase of drive upgrades
- Symptoms: Websites and email hosted on the affected server will be inaccessible during the maintenance window.
Planned maintenance: 1094 - Cape Town Data Centre move - 9 February 2025 (batch 1)
Completed
February 10 12:45 AM SAST
Completed
February 9 11:13 PM SAST
Completed
February 9 9:55 PM SAST
Scheduled
February 7 9:24 AM SAST
- Maintenance window: 8hr
- Attending: xneelo Engineers
- Summary: The following servers will be unavailable due to the relocation of our Cape Town Data Centre:
- Symptoms: Websites and email hosted on the affected server will be inaccessible during the maintenance window. For FAQs refer to our Help Centre article: https://xneelo.co.za/help-centre/products-and-services/data-centre-move-faq/
Planned maintenance: 1100 - Hardware Upgrade: Multiple shared servers
Completed
February 9 7:36 AM SAST
Scheduled
February 7 2:50 PM SAST
- Maintenance window: 1 hour
- Attending: xneelo Engineers
- Summary: Full hardware upgrade of 4 shared servers -better motherboard, CPU and RAM increase. www132.jnb2.host-h.net www85.jnb2.host-h.net www74.jnb2.host-h.net www538.jnb1.host-h.net.
- Symptoms: Websites and email hosted on the affected server will be inaccessible during the maintenance window.
Planned maintenance: 1092 - .COM, .NET Registry Maintenance
Completed
February 9 3:50 AM SAST
Scheduled
February 6 3:09 PM SAST
- Maintenance window: 45 min
- Attending: Registry Engineers
- Symptoms: During the maintenance window availability checks, registrations, renewals and updates for .com and .net domains may not be available.